ATC News release: Regulatory application filed with PSC for Rockdale-West Middleton Project

ATC submits regulatory application for Rockdale – West Middleton project to PSC Year-long regulatory review includes evaluation of need, alternatives and routes MADISON, Wis. – ATC today submitted to the Public Service Commission of Wisconsin its application requesting approval of a proposal for a new 345-kilovolt electric transmission line through Dane County between the towns […]

News release: ATC to clear right-of-way for line upgrade between Hartford and Saukville

Transmission line right-of-way to be cleared of vegetation 60-year-old poles and wires to be replaced between Saukville and Hartford WAUKESHA, Wis. – American Transmission Co. crews will be removing trees and clearing woody vegetation within an existing electric transmission line right-of-way between the Saukville Substation and the St. Lawrence Substation (located northeast of Slinger in […]

News release: Work to start along Michigan’s Upper Peninsula

Laurium Rebuild will improve electric reliability in Houghton County Kingsford, Mich. – American Transmission Co. will soon begin reconstruction of the existing transmission line that runs between the Atlantic Mine Substation, located in Adams Township, and the Osceola Substation, located in Calumet Township. “The upgraded transmission line will improve electric reliability in Michigan’s Upper Peninsula,” […]

Wisconsin State Journal Editorial: Don’t Short Circuit Power Line Plan

Opponents of American Transmission Co. have thrown everything but the kitchen sink in the way of the utility’s plans to ensure that the Madison area continues to receive an adequate, reliable supply of electricity. Now a group of opponents even wants to heave the sink. The group, led by Dane County Sup. Kyle Richmond of […]

News release: ATC to start work along Highway 41 in Oshkosh

Ellinwood-Sunset transmission line upgrade will improve electric reliability in Fox Valley De Pere, Wis. – American Transmission Co. will soon begin work on the existing transmission line that runs alongside US Hwy. 41 between the Sunset Point Substation, located in the town of Oshkosh, and the Ellinwood Substation, located in the City of Oshkosh. “The […]

PSC approved new transmission line near Waunakee

ATC gets approval to construct electric transmission line near Waunakee 138-kV line will ensure local electric reliability for existing customers and future growth MADISON, Wis. – Following a year-long regulatory review, the Public Service Commission of Wisconsin gave ATC its final approval today for construction of a new electric transmission line from Vienna to Westport, […]

PSC news release: Transmission line in Waunakee will provide needed relaibility for surrounding communities

IMAGE

News release: New electric transmission line energized in Oneida and Forest counties

Venus-Metonga transmission line completed on schedule De Pere, Wis. – American Transmission Co. placed in service last week a new 115-kilovolt electric transmission line connecting the Venus Substation, located in the Town of Monico, with a new Wisconsin Public Service Corp. substation, named the Metonga Substation, in Crandon. Construction began in late fall 2006 on […]

News release: Power line boosts reliability in Columbia County

Columbia-Rio transmission line completed under budget and ahead of schedule MADISON, Wis. – American Transmission Co. placed in service last week a new 69-kilovolt electric transmission line connecting the Columbia Substation, located in the Town of Pacific, with the Rio Substation, located in the Village of Rio. The new line will also connect to a […]

News release: Regulatory review begins on transmission access project (Paddock Rockdale)

PSC begins formal review of ATC’s application for Paddock – Rockdale Project 180-day regulatory analysis of electric transmission access proposal begins MADISON, Wis.—American Transmission Co.’s application seeking approval to construct a new 345 kilovolt electric transmission line in south central Wisconsin was declared complete last week by the Public Service Commission of Wisconsin. The determination […]