American Transmission Co. projects

Project website for a Wisconsin-based company that owns and operates the high-voltage electric transmission system that powers communities in portions of the Upper Midwest.

Media Line: (877) 506-6117info(at)atcllc.com

PSC gives verbal approval to ATC transmission line project

North Appleton-Morgan includes 345,000- and 138,000-volt lines, substation work

MADISON, Wis. – The three commissioners of the Public Service Commission of Wisconsin gave verbal approval to an electric reliability project in northeastern Wisconsin today. At an open meeting, the commissioners agreed on the need for the North Appleton-Morgan Transmission Line Project and approved a route through Outagamie, Brown, Shawano and Oconto counties.

“The approval of the North Appleton – Morgan project by the Public Service Commission of Wisconsin represents a major step forward in strengthening the electric transmission grid in northeastern Wisconsin,” said David Hovde, senior local relations representative for American Transmission Co. “We will continue to work with landowners and other interested parties as we move into the construction phase of the project.”

As part of ATC’s Bay Lake Project announced in 2012, North Appleton-Morgan includes:

  • A new 345-kV line and a new 138-kV line between the North Appleton Substation on French Road in the Town of Freedom in Outagamie County and the Morgan Substation in Oconto County (about 40 to 48 miles depending on route),
  • Expanded facilities at North Appleton and Morgan substations,
  • A new Benson Lake Substation at the site of the Amberg Substation in Marinette County to accommodate a large voltage-control device and
  • Additional work at 11 substations in northern Wisconsin and Michigan’s Upper Peninsula.

ATC met with landowners, local officials and other interested stakeholders for nearly two years to develop route alternatives for the new transmission lines. Single-circuit, self-supporting steel monopole structures would be used in most locations. The typical height of the structures would be 85 feet on the 138-kV line and 120 feet on the 345-kV line.

Preliminary estimated cost of the project is $307 to $327 million; a more refined cost estimate will be included in the PSC’s final order for the project, which is anticipated to be issued within the next month.

Plans for the project will follow this general timeline:
Property owner notifications ……… June 2015
Begin easement negotiations………..Late 2015
Construction start……………………….July 2016
In-service date……………………………Second quarter 2019

Note to editors: A high-level map of the project’s route, along with other information, is available at www.BayLakeProject.com

The project application and other documents associated with the regulatory review process are available at www.psc.wi.gov under Docket No. 137-CE-166.

###

# # #

ATC is a Wisconsin-based company that moves energy along the regional electric grid in parts of Wisconsin, Michigan, Minnesota and Illinois, serving more than 5 million electric consumers. We are experts at what we do: planning, maintaining, operating and protecting the grid. As the electric industry moves toward renewable generation sources, we are transforming our system to continue delivering energy reliably and safely. We proudly support STEM education programs that empower youth with the skills needed to succeed in tomorrow’s energy workforce. For more information, visit www.atcllc.com and follow us on LinkedIn and X (Twitter).