ATC Projects home
  ATC Projects News and ViewsAbout ATCContact ATC

We'd like to hear from you!

Thoughts on this project? Questions about the process? Comments? Email Lee Meyerhofer or call 866-899-3204, ext. 6572.    
Media Contact: 877-506-6117

   

 Interactive potential corridor map
  RELATED PROJECT INFORMATION:
   

Potential corridors map

Potential corridors by county (including municipalities)

Project fact sheet

Interstate connections fact sheet

Renewable energy fact sheet

6-2-11 news release

9-8-10 news release

7-26-10 news release

IN THE NEWS:
Wisconsin State Journal: Public input pays off in power plan Read the article

Wisconsin State Journal editorial supports Badger Coulee line Read the article

Badger Coulee project planning

  TRANSMISSION LINE TOPICS:
 
Construction practices
Easements and right-of-way
Electric and magnetic fields
Environment
Find projects by map
Frequently asked questions
Glossary
Links
List of transmission projects
Projects completed and in service
Property value
Public involvement and outreach
Regulatory review process
Stray voltage
Structures and facilities
Trees & vegetation
Underground lines
BADGER COULEE TRANSMISSION LINE PROJECT  
 

American Transmission Co. has plans for a high-voltage transmission line in western Wisconsin that would address electric system reliability issues locally and in the Midwest, provide economic savings and support renewable energy policy. The area, from north of La Crosse to northern Dane County, is being considered as a possible corridor for the approximately 150-mile, 345-kilovolt line.

ATC's studies indicate that the Badger Coulee Transmission Line Project is a multi-benefit project that would deliver benefits to Wisconsin and the Midwest region in three important ways:

Improve electric system reliability locally and regionally

  • Better enable Wisconsin to import power
  • Offset the need for approximately $180 million ($140 million in the ATC service area) in lower voltage upgrades in western Wisconsin communities
  • Alleviate stability issues on regional transmission grid

Deliver economic savings for Wisconsin utilities and electric consumers

  • Provide utilities with greater access to the wholesale electricity market with potential savings that can be passed on to electric consumers
  • Improve efficiency of grid; more efficient grid reduces the cost to deliver energy
  • Connect to high-quality renewable resources in the nation's western wind alley, which translates into hundreds of millions of dollars in potential savings

Expand infrastructure to support public policy for greater use of renewables

  • Establish another pathway for renewable energy into Wisconsin with connections to key load centers
  • Match regional studies (Strategic Midwest Area Transmission Study and Midwest ISO Regional Generation Outlet Study) evaluating transmission options that best deliver renewable energy while also addressing reliability issues

Public involvement

ATC has a practice of engaging the public and other interested stakeholders in its proposed transmission line projects as a way to identify possible routes far in advance of filing a regulatory application with the Public Service Commission of Wisconsin. While the studies are not yet completed on this project, ATC began engaging the public through open houses in fall 2010. Click here to learn more about ATC’s public involvement process.

PROJECT AT A GLANCE
Area benefited: Western Wisconsin communities, the state of Wisconsin and the entire Midwest region
Line length: Approximately 150 miles
Voltage: 345,000 volts
Project Cost: Approximately $425 million
End points: The southern end point of the line will be the North Madison Substation in the Town of Vienna, continuing to the Cardinal Substation in the Town of Middleton. The northern end point of the line has not yet been determined.
PSC Project Docket ID: 137-CE-160 Click here to visit the PSC website.

 

SCHEDULE*
Identify potential routes with public involvement:

Fall 2010-2012

Submit application to Public Service Commission:
2013
Receive PSC decision:
2014
Begin construction:
2016
In-service date:
2018
*Dates are anticipated and subject to changes