Branch River Substation
A new substation is needed in Manitowoc County to provide electric system stability. The Branch River Project involves building a new 345-kV substation and associated 345-kV transmission lines in the Manitowoc County Town of Franklin.
Project at a Glance
Counties affected: | Manitowoc |
Line length: | Short sections of 345-kV line to tie existing lines into the substation; relocation of some 138-kV lines in the area to new structures on new right-of-way |
Voltage: | 345-kV |
Schedule*
Public outreach: | Spring and Summer 2014 |
Environmental analysis: | Spring and Summer 2014 |
File CPCN application: | Fall 2014 |
Regulatory review & public comment: | 2014-15 |
Approval from PSCW: | July 2015 |
Construction start: | 2017 |
In-service: | First quarter 2018 |
*Dates are anticipated and subject to changes |
---|