American Transmission Co. projects

Project website for a Wisconsin-based company that owns and operates the high-voltage electric transmission system that powers communities in portions of the Upper Midwest.

Bay Lake Project – Michigan

Holmes-Old Mead Road

  • A single-circuit 138-kV line from the Holmes Substation in Menominee County to the Old Mead Road Substation in Escanaba.

When the Bay Lake Project was originally proposed, it included two new 138-kV lines between Menominee County and Escanaba. It was subsequently determined that a single transmission line will be adequate for the foreseeable future. This change allowed us to review opportunities to co-locate with existing transmission lines to minimize the amount of new right-of-way required. The proposed routes maximize the use of existing transmission line corridors and an abandoned railroad corridor.

ATC has a practice of engaging the public and other interested stakeholder in its proposed transmission line projects as a way to identify possible routes far in advance of filing a regulatory application. ATC began engaging the public through open houses in May 2012.

Learn more about ATC’s public involvement process.

Project at a Glance
Areas that benefit:Upper Peninsula of Michigan
Counties where facilities may be located:Delta and Menominee
Line length:58 miles
Voltage:138-kV
Estimated project cost:$94 million
End points:Holmes Substation in Menominee County, Mich., to Old Mead Road Substation in Escanaba, Mich.
*estimates will be refined as project design becomes more detailed
Schedule*
Public information and involvement, including routing and siting:Spring 2012-2013
Environmental analysis:2012-2013
File regulatory application with Michigan Public Service Commission:Fall 2013
Regulatory review & public comment:2013-2014
Anticipated regulatory decision:Early 2014
Start construction:Early 2015
Target in-service date:Summer 2016
*Dates are anticipated and subject to changes