Overview
American Transmission Co. will soon begin rebuilding the 18-mile, 69,000-volt electric transmission line that connects the Brodhead Substation and South Monroe Substation in Monroe. The age and condition of the existing line, which was built in 1950, necessitated the rebuild.
The new line will make a vital improvement in the reliability of the electric transmission system serving the area and will help ensure that the south central Wisconsin area is served by a reliable electric delivery system in years to come. The voltage of the line will not change, but the replacement structures and line will be designed to accommodate increased electric demand and to support growth.
The new line will follow the route of the existing line, and the work will involve installing new poles, wires and insulators. Construction is scheduled to begin spring 2011 and is projected to continue through December 2011.
At a glance
Line length: 18 miles
End points: Brodhead Substation and the South Monroe Substation in Monroe
Voltage: 69,000 volts
Estimated cost: $12 million |
 |
Weathering steel poles (appear brown in color) will be used for the majority of the 18-mile line. |
Schedule*
PSC approval of project: April 2009
Construction start: Spring 2011
Anticipated in-service date: December 2011
*Subject to changes
To view a copy of the PSC’s order, visit the PSC website at psc.wi.gov and use Docket Number: 5-AE-178 in the Electronic Regulatory Filing System.
|
 |
For more information or to comment on this project, e-mail Charlie Gonzales or call 866-899-3204, extension 3644.
|
|