ATC Projects home
  ATC Projects News and ViewsAbout ATCContact ATC

We'd like to hear from you!

For more information or to comment on
this project, email Jon Callaway or
call 866-899-3204, ext. 3540.

Media contact: 877-506-6117

  RELATED PROJECT INFORMATION:
   
Project area map
February 2007 newsletter
 
  TRANSMISSION LINE TOPICS:
 
Construction practices
Easements and right-of-way
Electric and magnetic fields
Environment
Find projects by map
Frequently asked questions
Glossary
Links
List of transmission projects
Projects completed and in service
Property value
Public involvement and outreach
Regulatory review process
Stray voltage
Structures and facilities
Trees & vegetation
Underground lines
DODGE COUNTY  
 

Project overview

ATC placed into service approximately 14 miles of new 138-kilovolt transmission line connecting a new substation located east of Horicon to an existing substation south of Neosho.


The electric transmission system that serves the communities of Beaver Dam, Hustisford, Horicon and central Dodge County will benefit from a more reliable system to serve the growing area. Previously, the electric system was operating at maximum capacity and could not accommodate growth in electric usage or maintain service in the event of an equipment failure.

PROJECT AT A GLANCE
Communities affected: Rubicon, Neosho, Hustisford, Horicon. All of central Dodge County will benefit from this transmission upgrade.
Line length: Approximately 15 miles
Voltage: 138,000 volts
Final cost: $22 million
End points: Substation near Horicon and Rubicon Substation south of Neosho.

 

SCHEDULE
Public open houses:
Fall 2005
Submitted application to Public Service Commission:
February 2006
Receive PSC decision:
December 2006
Began construction:
Fall 2007
In-service date:
May 2008