ATC Projects home
  ATC Projects News and ViewsAbout ATCContact ATC
  TRANSMISSION LINE TOPICS:
 
Construction practices
Easements and right-of-way
Electric and magnetic fields
Environment
Find projects by map
Frequently asked questions
Glossary
Links
List of transmission projects
Projects completed and in service
Property value
Public involvement and outreach
Regulatory review process
Stray voltage
Structures and facilities
Trees & vegetation
Underground lines
CHOOSING A ROUTE FOR A NEW TRANSMISSION LINE  
 

The routes for a transmission line project are developed in sequential phases beginning with many potential routes and narrowing to a few options. The input and feedback is used at each phase to help guide decisions about potential routes. ATC believes that the perspectives of those most familiar with the impacted areas can help improve the outcome of the routing and siting process, and lead to a better overall project that is more acceptable to those most impacted. Through the input received from the public, regulatory agencies and other stakeholders, we consider options that are appropriate for the location and issues associated with a particular project, and consistent with routing criteria under state laws.

 

Transmission line routing involves trade-offs between a variety of factors. The route options that are most promising balance community input with environmental impacts, constructability, current and future land use, project costs and specific electric system needs.

  

At ATC we use an open and inclusive approach at four distinct phases of route development for a transmission line.  (Note: Smaller projects may follow fewer than four phases)

Phase 1:  Study area

Once we have determined the end points (usually two substations) for a new transmission line, we begin with a study area that is usually a large geographic area from which we'll identify potential corridors that may be suitable for a transmission line.

 

 

Phase 2: Preliminary corridors 

Based on routing criteria and public input, preliminary corridors are identified within the study area. We generally identify several corridors (can be several hundred feed wide or more) between the end points that may be suitable for a transmission line route, but at this point the corridors have not yet been thoroughly evaluated. These preliminary corridors represent opportunities to rule in or rule out possible routes, and are presented to the public for discussion and input.

Phase 3: Proposed route options

It may take several months to move from preliminary corridors to proposed route options. The proposed routes represent those that are "still on the table" and include a more defined, narrow set of the preliminary corridors than those introduced during Phase 2. The proposed routes have been evaluated more thoroughly and are likely to be considered for the project.

Phase 4: Final proposed routes

These are the routes (two or more) that have been identified based on environmental and land use consideration, suitability for construction, public acceptance, cost and electric system needs. These routes are formally presented in the construction application that ATC submits to the Public Service Commission of Wisconsin for authorization. ATC is required to submit at least two possible routes along with supporting environmental, engineering and construction information. We sometimes recommend a particular route which we designate as the preferred route. However, the PSC does not consider our designation in their analysis.