Project overview
American Transmission Co. completed work on the existing transmission line that runs alongside US Highway 41 between the Sunset Point Substation, located in the town of Oshkosh, and the Ellinwood Substation, located in the City of Oshkosh.
The work involved added a second circuit (set of wires) to the existing 3.8 miles making the existing line a double circuit line. To accommodate the second circuit, it was necessary to replace six structures with steel poles on concrete foundations, as well as adding six new steel poles. The remaining structures were fitted with new "arms" to carry both the existing circuit and the new circuit. Work was also done at both substations.

At a glance
Communities affected: City and Town of Oshkosh
Length of line: Approximately 3.8 miles
End points: Ellinwood Substation and Sunset Substation
Voltage: 138 kilovolts
Status of project: Completed
Schedule
Construction start: August 2007
In-service: December 2007
For more information or to comment on the project, e-mail David Hovde or call 866.899.3204, ext. 6550.
|