ATC Projects home
  ATC Projects News and ViewsAbout ATCContact ATC
  RELATED PROJECT INFORMATION:
   
Project area map
 
 
  TRANSMISSION LINE TOPICS:
 
Construction practices
Easements and right-of-way
Electric and magnetic fields
Environment
Find projects by map
Frequently asked questions
Glossary
Links
List of transmission projects
Projects completed and in service
Property value
Public involvement and outreach
Regulatory review process
Stray voltage
Structures and facilities
Trees & vegetation
Underground lines
CYPRESS SUBSTATION  
 

Project overview

ATC is providing a transmission interconnection for a wind generation facility being constructed by We Energies. The name of the wind farm project is called Blue Sky Green Field and is located in northeast Fond du Lac County. The entire wind farm will be comprised of 88 wind turbines.

At a glance

Communities affected: Towns of Calumet and Marshfield, Fond du Lac County
Status of project: Substation currently under construction


Schedule
Public outreach: Ongoing
Start of construction: June 2007

Anticipated completion: January 2008

 

 

 

 

For more information on this project or to comment, e-mail David Hovde or call 866.899.3204, ext. 6550.