Project overview
Electricity demand in Door County has been growing at an aggressive rate. The 69-kilovolt transmission system serving the northern portion of Door County is quickly reaching its capacity. In addition, most of the northern portion of the county, being served by a single line, is vulnerable to extended interr uption of service if that single line suffered an extended outage. Without reinforcements, this system will be susceptible to facility overloads and unacceptably low voltages. Improvements to the transmission system will provide significant voltage support and provide additional transformation capacity to the northern Door County area.
PROJECT AT A GLANCE |
| Communities affected: |
City and Town of Sturgeon Bay; Town of Sevastopol |
| Line length: |
Scope still being determined |
| End points: |
Canal Substation and the Dunn Rd. Substation |
Project status: |
Public outreach underway |
SCHEDULE* |
| Public information and involvement: |
Fall 2008 |
| Submit application to Public Service Commission: |
November 2009 |
| Anticipated PSC decision: |
Fall 2010 |
| Begin construction: |
Summer 2011 |
| In-service: |
Summer 2012 |
| *Dates are anticipated and subject to changes |
|