ATC Projects home
  ATC Projects News and ViewsAbout ATCContact ATC
  RELATED PROJECT INFORMATION:
   
Project area map
Project newsletter (July 2007)

Project newsletter (February 2008)

Also see Conover - Plains Project

  TRANSMISSION LINE TOPICS:
 
Construction practices
Easements and right-of-way
Electric and magnetic fields
Environment
Find projects by map
Frequently asked questions
Glossary
Links
List of transmission projects
Projects completed and in service
Property value
Public involvement and outreach
Regulatory review process
Stray voltage
Structures and facilities
Trees & vegetation
Underground lines
CRANBERRY-CONOVER  
 

Project overview

Construction is ongoing for a new 138-kilovolt, 16-mile line between Eagle River and Conover. This line is scheduled to be energized in June 2008.  Construction will then continue on a related project between the Conover Substation and the Plains Substation in Norway, Mich.

The electric transmission infrastructure serving northern Wisconsin and the western Upper Peninsula of Michigan is in need of reinforcement. Significant growth has occurred in the Rhinelander/Eagle River area, resulting in an overloaded system that is vulnerable to interruptions and even blackouts under severe conditions. The lines to the east that connect northern Wisconsin and the Upper Peninsula are the most severely constrained in the ATC system. The constraints limit ATC's ability to move power in and out of the Upper Peninsula, requiring higher-cost generators on the system to run more often, costing ATC customers million of dollars a year. In addition, there is limited ability to schedule maintenance on these lines, resulting in reduced reliability and increased operating costs.

At a glance
Communities affected: Eagle River, Conover and Florence, Wis.; improved reliability will benefit northern Wisconsin and the western areas of the Upper Peninsula
Length of line: 16 miles
End points: Cranberry Substation in Eagle River to Conover Substation in Conover

Voltage: 138 kilovolts
Status of project: In construction; expected completion June 2008.

Schedule
File construction application to PSC: November 2005
Regulatory review and public comment: Late 2005
Project approval from PSC: November 2006
Start of construction: August 2007 (Cranberry-Conover)

Anticipated completion: June 2008 (Cranberry-Conover)


For more information or to comment, e-mail Lee Meyerhofer or call 1-866-899-3204, ext. 6572.