Project overview - Complete and energized
Construction was completed in June 2008 for a new 138-kilovolt, 16-mile line between Eagle River and Conover. Construction will then continue on a related project between the Conover Substation and the Plains Substation in Norway, Mich.
The electric transmission infrastructure serving northern Wisconsin and the western Upper Peninsula of Michigan is in need of reinforcement. Significant growth has occurred in the Rhinelander/Eagle River area, resulting in an overloaded system that is vulnerable to interruptions and even blackouts under seve re conditions. The lines to the east that connect northern Wisconsin and the Upper Peninsula are the most severely constrained in the ATC system. The constraints limit ATC's ability to move power in and out of the Upper Peninsula, requiring higher-cost generators on the system to run more often, costing ATC customers million of dollars a year. In addition, there is limited ability to schedule maintenance on these lines, resulting in reduced reliability and increased operating costs.
PROJECT AT A GLANCE |
| Area benefited: |
Eagle River, Conover and Florence, Wis.; improved reliability will benefit northern Wisconsin and the western areas of the Upper Peninsula |
| Line length: |
16 miles |
| Voltage: |
138,000 volts |
| End points: |
Cranberry Substation in Eagle River to Conover Substation in Conover |
| Status of project: |
Completed June 2008 |
| Related project: |
Conover-Iron River-Plains |
SCHEDULE |
| File construction application to PSC: |
|
| Regulatory review and public comment: |
Winter 2005 |
| Receive PSC decision: |
Nov. 2006 |
| Begin construction: |
|
| In-service date: |
|
|