Project Overview
American Transmission Co. plans to rebuild an existing electric transmission line that connects the Monroe County Substation near Sparta and the Council Creek Substation near Tomah. ATC also will build a new substation as part of the project.

The project involves replacing the structures and wires of the existing 69-kilovolt transmission line, and adding a 161-kilovolt circuit to the new steel structures. Transmission line work will be completed within the existing right-of-way area. To allow for flexibility on the 69-kilovolt system, ATC also will build the new Timberwolf Substation approximately 1/2 mile south of Interstate 90 along Highway 131.
The existing 69-kilovolt transmission system that serves the area is approximately 40 years old and is susceptible to overloads and severe low voltages. Rebuilding the 17-mile line and adding the new 161-kilovolt circuit will strengthen the reliability of the electric system that serves the area. In addition, the new line will provide economic savings by increasing the system’s ability to access lower-cost generation and reducing energy losses.
PROJECT AT A GLANCE |
| Communities affected: |
City of Sparta, Town of Angelo, Fort McCoy Military Reservation, Town of Adrian, Town of Tomah, City of Tomah |
| Line length: |
Approximately 17 miles |
| Voltage: |
161-kV and 69-kV |
| Cost: |
Approximately $36 million |
| End points: |
Monroe County Substation in Sparta and Council Creek Substation near Tomah |
PSC Project
Docket ID: |
137-CE-158 Click here to visit the PSC website. |
SCHEDULE* |
| Public open houses: |
Summer-Fall 2010 |
| Submit application to Public Service Commission: |
July 29, 2010 |
| Regulatory review: |
Fall 2010 |
| Receive PSC decision: |
January 2011 |
| Begin construction: |
Summer 2012 |
| In-service date: |
Summer 2013 |
| *Dates are anticipated and subject to changes |
|